Bucharest Mayor Ciprian Ciucu inspected ongoing replacement work on heating pipes along Calea Văcărești, discovering the project is significantly behind schedule, currently only 30% complete. The work was originally slated for completion, prompting concern from city officials. During the inspection, Ciucu found a minimal workforce of only three laborers at one work site. The city administration has already issued a notice to the contractor demanding increased mobilization to accelerate progress. Ciucu warned that delays could jeopardize funding for the project. He urged companies involved in the project’s consortium to collaborate and ensure timely completion.